The SEZ consists of Building structures with a total built-up area of about 7165 sq.m has an estimated total cost of Nrs.292 Million. The Road network system for the project includes a 4-lane asphalt concrete pavement of length 9.944 Km with a total estimated cost of Nrs.718 million.
The Water Supply system including the water distribution system, water treatment and RCC overhead water storage (2x400 cum and 1x100cum) has an estimated cost of Nrs.371 million. Storm water network drainage system for providing drainage from buildings, industries, road and open area costs an estimated Nrs.432 million.
Waste water network system and waste water treatment system has a close type distribution system with manhole as well as oxidation ponds, waste stabilization ponds for treating 958 MLD per day at a construction cost of NRs.58 million
Other Civil structures includes boundary wall, industrial plots, main entrance gate, security check posts, pump house, parking areas for heavy and light vehicles, open spaces and site development works and green areas, petrol pump, truck weighing bridge at an estimated cost of Nrs.690 million
Electrical works and telecommunication works have a combined construction cost of Nrs.805 million
The total estimated project cost including contingencies and VAT is NRs.5 billion.